Reinforced concrete works on the joints of the new shopping center City Center One Split are coming to an end.
The works on the garages are in the initial phase after the problems caused by water precipitation on the construction site are being solved.

 

After the performance of  broad pit excavation, foundation preparation and construction site protection, on the one part of the facility, concrete base slab was done. Concrete insulation was done, protected by a layers of insulating material. When the first part of the concrete core slabs will be ready, we will set up a crane on it in the next few days.




At this moment, on one of the largest and most complex construction sites in Croatia, City Center One - Split, our company performed reinforced concrete work on the monolithic construction of the building.
City Center One Split building site consists of two parts: the main building and parking lots. The main building consists of 3 parts (dilatations). Works are carried out on schedule. In the final phase of work on the dilatation of D1, is ongoing dismantling the set 4 out of 5 cranes. You can follow the progress in live via two web cameras directly from the construction site City Center One - Split.
Start of the works in the parking lot is planned for January, 2010.
Our work performed by 270 workers is a guarantee that the construction will be done by July 2010

Photos from the construction site City Center One - Split: